Ed Sheeran, The Loop Tour, North America 2026
- Challenge: 21 stadiums, most of whose operations teams had never been asked how much charging capacity their grid connection could give a touring production. Every site had to be planned with the venue well before load-in.
- Objective: Run the tour’s power on the SmartGrid, charged from each stadium’s own grid connection, with no touring-sized diesel generators.
- What we delivered: The SmartGrid was the primary power source for 16 dates on the US stadium tour, with no backup touring generator. It was charged from the stadium grid or, where grid capacity fell short, from 2 × 250 kVA charging generators at their maximum efficiency but too small to run the show on their own. Eight shows at seven stadiums ran with no generator used at all therefore
100% onsite emission-free100% on-site emission-free: State Farm Stadium*, Allegiant Stadium, MetLife Stadium* (x2), Lincoln Financial Field*, Mercedes-Benz Stadium*, Lucas Oil Stadium* and AT&T Stadium* (*Industry-first SmartGrid deployment)
- Outcome (16 SmartGrid shows, against a standard modelled generator package for each show):
- 90% reduction in power and energy CO2e
- 86,234 litres of diesel avoided (94.6%), an average of 5,389 litres per show
- 93% reduction in generator run time
- System: 1.25 MW / 1.68 MWh SmartGrid. No backup touring generator